How to Get New FESCO Electricity Connection in Sargodha: Complete 2026 Guide

Getting a new electricity connection in Sargodha District? This guide covers the complete process from application to meter installation.

By Ali Sherazi · Updated May 2026 · 12 min read

Time:
15-30 days for domestic connections
Cost:
Rs. 8,000 - 50,000 depending on connection type and load

The short answer

Apply at your local FESCO subdivision office with CNIC, property documents, and application fee (Rs. 500-2000 depending on load). Processing takes 15-30 days for domestic connections.

See our editorial policy. Fees and timings change, so confirm with the office before you go.

Required Documents Checklist
  • Original CNIC + 2 photocopies
  • Property ownership documents (Registry/Fard/Intiqal)
  • Affidavit on Rs. 50 stamp paper
  • 4 passport size photographs
  • NOC from landlord (if rented property)
  • Site map showing nearest FESCO transformer
  • Proof of internal wiring completion

Step-by-Step Guide

Follow each step in order. Do not skip steps — the sequence matters.

1Determine Your Connection Type

Domestic (A-1): For residential use. Commercial (A-2): For shops/offices. Industrial (B-1, B-2): For factories. Agricultural (Tubewell): For farming. Each has different tariffs and requirements.

Pro Tip: Choose carefully - changing connection type later requires a new application and fees.

2Calculate Your Load Requirement

Single Phase: Up to 5 kW (most homes). Three Phase: 5-500 kW (large homes, shops, industries). List all your planned appliances and their wattage to determine required load.

3Gather Required Documents

Original CNIC + 2 copies. Property ownership proof (Registry/Fard). Affidavit on stamp paper (Rs. 50). Passport size photos (4 copies). NOC from landlord (if rented). Site map showing nearest transformer.

Pro Tip: Get the affidavit from a Notary Public near Katchery. Cost: Rs. 200-300.

4Submit Application at FESCO Office

Visit your subdivision office during working hours (8 AM - 2 PM). Submit form with all documents. Pay application fee (Rs. 500 domestic, Rs. 1000 commercial, Rs. 2000 industrial).

5Wait for Site Inspection

FESCO lineman will visit your location within 7-10 days to verify the site, check transformer availability, and assess wiring requirements. Be present during inspection.

Pro Tip: Ensure your internal wiring is complete before inspection. FESCO won't connect without proper wiring.

6Pay Connection Charges

After approval, pay the demand notice amount at any designated bank. Domestic single-phase: Rs. 5,000-15,000. Commercial: Rs. 15,000-50,000. Industrial: Rs. 50,000+. Keep the receipt.

7Meter Installation

Within 7-14 days of payment, FESCO will install your meter. They'll provide a reference number and first bill. Verify meter reading is zero at installation.

Common Mistakes to Avoid

These are the most frequent reasons people waste a whole trip to the government office.

Applying without complete property documents

Get your property papers in order first. Visit Tehsil office for Fard if needed.

Underestimating load requirement

Always apply for slightly more load than current needs. Upgrading later costs more than initial higher load.

Not getting internal wiring done before application

FESCO requires complete wiring for inspection. Hire a licensed electrician to wire your premises first.

Paying to unauthorized agents

Only pay at FESCO office or designated banks. Get official receipts for every payment.

Frequently Asked Questions

How long does it take to get a new connection?

Domestic: 15-30 days. Commercial: 20-45 days. Industrial: 30-90 days (depending on load and transformer availability).

What is the cost of a new domestic connection?

Total cost including application fee, security deposit, and connection charges: Rs. 8,000-20,000 for single phase, Rs. 25,000-50,000 for three phase.

Can I apply online?

Partial online application is available at fesco.com.pk, but you still need to visit the office for document verification and payment.

What if my area doesn't have a transformer?

You may need to share the cost of a new transformer with neighbors, or wait until FESCO installs one. Contact the SDO for options.

Helplines & Offices

Helpline numbers shown here are national short codes. Office timings are typical and can change, so confirm locally before you travel.

FESCO Customer Service

118

24/7

Sargodha City SDO Office

8 AM - 2 PM